Wexford County Council has confirmed that Enniscorthy's €1.2 million interim flood protection measures will not provide full protection against future flooding, with several elements of the programme still outstanding.
In response to questions from South East Radio, the Council has provided a detailed update on the town's flood protection measures following the severe flooding experienced earlier this year.
Floodwall works at the Promenade car park and Abbey Quay have now been completed, while the Council has also taken delivery of new AquaDams, designed to provide temporary flood barriers during emergencies.
However, earth-bank works around the swimming pool, which had originally been expected to be completed by mid-November, remain outstanding.
Wexford County Council says these works are now expected to be installed in the coming weeks, although no firm completion date has been provided.
AquaDam emergency exercise confirmed for December 6th
The Council has confirmed that an emergency deployment exercise involving the new AquaDams will take place at 9am on Sunday, December 6th.
Local residents, businesses and members of the media will be permitted to observe the exercise.
Concerns had been raised about whether the new barriers would be ready for use if further flooding occurred before the planned exercise.
In response, the Council confirmed that AquaDams borrowed from another local authority are already available for emergency use, while the newly delivered barriers will undergo testing.
The areas identified in the Council's update include Island Road, the Promenade car park and Abbey Quay.
Full flood protection still some way off
Despite progress on the interim measures, Wexford County Council has acknowledged that they will not provide full protection against severe flooding.
Asked whether the measures could withstand an event similar to Storm Chandra, the Council said they were intended as temporary protection only.
It confirmed that full flood protection can only be provided through the permanent Enniscorthy Flood Relief Scheme.
Individual property protection measures, which had previously been scheduled for installation before the end of 2026, are also awaiting delivery.
The Council says these have been ordered but have not yet arrived.
Replacement bridge planning expected in early 2027
Wexford County Council has also provided an update on the long-awaited permanent Enniscorthy Flood Relief Scheme.
It expects the planning application process for Phase 1, involving the proposed replacement bridge, to begin during the first quarter of 2027.
Meanwhile, procurement of design team consultants for Phase 2 of the scheme has commenced.
The update comes amid continuing concern among Enniscorthy residents and businesses about the town's vulnerability to flooding.
While several elements of the interim protection programme have been completed, outstanding works and the limitations of the temporary measures mean Enniscorthy is still awaiting the comprehensive protection envisaged under the permanent scheme.
Ballindaggin Pupils Become Water Conservation Champions During Science Week
Calls For HSE Accountability Over MRI Restrictions As Chief Executive Exits
Wexford Medical Centres Lead The Way In Campaign To Support Men Living With Incontinence
Cargo Vessel Fast Jef Successfully Refloated Off Wexford Coast
Comments
Add a comment